shot-button
Ganesh Chaturthi Ganesh Chaturthi
Home > News > India News > Article > Some train services to be disrupted due to block between Chalthan and Gangadhra stations says Western Railway

Some train services to be disrupted due to block between Chalthan and Gangadhra stations, says Western Railway

Updated on: 16 October,2023 07:41 PM IST  |  Mumbai
mid-day online correspondent |

The Western Railway said that the block will be operated on both the UP and Down lines along the Surat-Bhusaval line of the Tapti Valley section

Some train services to be disrupted due to block between Chalthan and Gangadhra stations, says Western Railway

Representational Pic/File

Some Western Railway trains will be affected by a scheduled block occurring between Chalthan and Gangadhra stations from the 18th to the 22nd of October, 2023. The block is essential for the launching of a 36-meter composite girder as part of a road overbridge (ROB) construction project, the Western Railway said in a statement.


It said, this block will be operated on both the UP and Down lines along the Surat-Bhusaval line of the Tapti Valley section.



Western Railway officials have announced the rescheduling of several trains due to this block, affecting passenger travel plans. The Chief Public Relations Officer, Shri Sumit Thakur, issued a press release detailing the rescheduled trains as follows:


Train No. 19046 Chhapra – Surat Tapti Ganga Express: Passengers with journeys commencing on the 17th, 18th, and 21st of October, 2023, will experience a 2-hour rescheduling.

Train No. 09378 Nandurbar – Udhna MEMU: Travelers planning journeys from the 18th to the 22nd of October, 2023, will face a 1-hour rescheduling.

Train No. 22948 Bhagalpur – Surat SF Express: Passengers scheduled to travel on the 19th of October, 2023, will experience a 2-hour rescheduling.

Passengers affected by these rescheduled journeys are kindly requested to take note of the changes in their travel plans. The Western Railway authorities have taken these measures to ensure passenger safety and to facilitate the construction of the important road overbridge.

In an another statement, the Western Railway said that Varanasi Yard remodelling was commissioned on October 15.

It said, a massive 663 route EI having 283 signals, 214 points along with block working in 6 directions including yard modification involving 158 new Turnouts and track linking with RE of nearly 38 km has been commissioned after tireless hard work and meticulous planning. This involved laying of 38 km new track equivalent to doubling of more than 38 km.

Its key features include-

1. Routes-  663

2. New Touts- 158 

3. Dismantling Touts- 122

4. New track laying- 38 km

5. Dismantling track- 17km

6. New signals- 283

7. Electrical TRD Work
(a)Wiring done- 40 TKM
(b) Wiring dismantled- 13 TKM
(c) 3 nos 11 KV compact sub-station installed & commissioned.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK