shot-button
Maharashtra Elections 2024 Maharashtra Elections 2024
Home > Mumbai > Mumbai News > Article > Mumbai pothole menace Lack of funds cold mix lead to delay in road repair work

Mumbai pothole menace: Lack of funds, cold mix lead to delay in road repair work

Updated on: 22 September,2022 07:50 AM IST  |  Mumbai
Prajakta Kasale | prajakta.kasale@mid-day.com

mid-day investigation reveals no new contractor wanted to take up work, and worse, even before rains, BMC had readied just two thirds of the required quantity of raw material

Mumbai pothole menace: Lack of funds, cold mix lead to delay in road repair work

A pothole-ridden road in Bhaucha Dhakka, Mazagaon. Pic/Pradeep Dhivar

If you are wondering why the BMC is not filling up potholes, it is because the civic body has not only already used up all of its cold mix in August but also surpassed the funds allotted for the same. Some ward officials also claimed that they are applying for additional funds. In addition, BMC did not receive any response from contractors for repairing the roads using new techniques. In the absence of its own cold mix, wards are depending on contractors appointed by the BMC for repairs.


Before every monsoon, the Brihanmumbai Municipal Corporation starts preparations to repair potholes during rains and produces cold mix in its Worli plant. This mix is then distributed to its 24 wards. In addition, the civic body, which divides the 24 wards into 7 zones, allots separate budgets for each zone and appoints contractors to take on the road repair work.


BMC’s cold mix


While the Worli plant produced around 2,150 metric tonnes of cold mix this year, the demand from all the wards was around 3,000 metric tonnes. The BMC had distributed 1,500 metric tonnes of cold mix before June and had kept the remaining in reserve. The reserve too was put to use by August. 

A BMC employee said that they used the cold mix to fill potholes after receiving complaints, but “it is not of much use as the mix comes out in a few days due to the rain”.

Also read: Need to end the pothole menace once and for all

Huge potholes cover the road near Pratiksha Nagar bus depot. Pic/Atul Kamble
Huge potholes cover the road near Pratiksha Nagar bus depot. Pic/Atul Kamble

“Cold mix cannot be produced during the rainy season due to high levels of moisture in the air. So it is prepared in the dry months and stored. The cold mix was distributed before June and even the mix which was kept in storage ended in August,” said a BMC official on the condition of anonymity. 

This means, since August BMC staffers have not been able to fill any potholes and are completely dependent on contractors. 

“When we asked for cold mix, we were told to get the contractors to fill up the potholes instead.  But, even private contractors are facing issues in getting the material owing to the season. As rains have not subsided yet, it has also led to worsening of roads,” said another BMC official. 

Contractors

This year, BMC had appointed contractors and allocated Rs 6 crore for each of the seven zones to repair the roads during monsoon. Several zones have already overshot the budget even as three weeks of monsoon is still remaining. 

In addition, the civic body had floated additional tenders in July for using new techniques, such as rapid hardening concrete and geo-polymer solution, at a cost of Rs 7 crore. However, all of the three new methods which were tried proved to be unsuccessful, and the civic body did not get responses to the tenders which stated that the contractor would get 50 per cent of the payment only after the defect liability period of 15 years. 

‘Need more funds’

A BMC ward official said they have now started applying for additional budgets. “Pothole-ridden roads make life miserable for commuters. We understand the issues faced by the citizens, but we need a few sunny days to complete the task,” said the official. 

Of the 2,050-km road network in the city, around 990 km are cement concrete and the rest are asphalt roads. The BMC has already passed the works of converting 236 km of asphalt roads into cement concrete and tenders for another 400 km have been floated. “Though the roads are selected for conversion into cement concrete and some of the roads will be taken for resurfacing, we have to take care of them till the work order is issued. Till then it is BMC’s duty to make these free of potholes,” a ward official said.

Additional Municipal Commissioner P Velarasu remained unavailable for a comment. Ulhas Mahale, deputy municipal commissioner of infrastructure, said that they haven’t received any specific request from ward levels and need to take details from each ward about the cold mix consumption and allocation of budget for contractors.

3,000 mt
Quantity of cold mix wards asked for from BMC

2,150 mt
Quantity of cold mix BMC distributed this year

August
Month when the 2,150 MT of cold mix got over

Three
No of weeks before the rainy season in Mumbai ends

Rs 6 cr
Fund allotted to each of the 7 zones in city for contractors

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK