shot-button
Maharashtra Elections 2024 Maharashtra Elections 2024
Home > Mumbai > Mumbai News > Article > Mumbai local train update Central Railway completes platform widening work at Thane after 63 hour mega block

Mumbai local train update: Central Railway completes platform widening work at Thane after 63-hour mega block

Updated on: 02 June,2024 12:53 PM IST  |  Mumbai
mid-day online correspondent |

The CR shared details about the special block for infrastructure upgrade work at Thane station

Mumbai local train update: Central Railway completes platform widening work at Thane after 63-hour mega block

Pic/PTI

The Central Railway (CR) on Sunday said it has completed widening work of platforms 5 and 6 at Thane.


The CR shared details about the special block for infrastructure upgrade work at Thane station. It said the platform 5/6 has been widened by 2-3 metres over a length of 587 metres.


Mumbai local train update: 'Historic work completed'


The CR in a post on 'X' said, "Historic work on widening of Thane station's platform 5/6 completed! Widening of Platform 5/6 by 2-3 meters for 587 meters length. Use of 750 pre-cast hollow blocks. Coordination of 400 laborers, 20 teams, and 10 contractors. Minimal disruption despite 935 train cancellations Efficient execution with zero delays! Work carried out along with NI work of CSMT, one of the busiest coaching terminals of Indian Railways. Deep appreciation to the work force for their meticulous planning, precision at work and timely execution."

Swapnil Nila, CR's chief public relations officer, said in a post on 'X': "First trial rake of EMU successfully traversing over widened PF5 at Thane. Thane work completed before schedule. Thank you Mumbai."

Mumbai local train update: The 63-hour mega block

The Central Railway had initiated a 63-hour mega block at Thane railway station and a 36-hour special block at the Chhatrapati Shivaji Maharaj Terminus. The mega block began at midnight on May 30-31 (Thursday-Friday night).

The platform widening project involved the use of 750 pre-cast hollow blocks and required the coordination of 400 workers, 20 teams and 10 contractors, a CR official said.

As many as 935 trains were cancelled during the 63-hour period, the official said.

The mega block for the widening of platform numbers 5 and 6 at Thane station started from Thursday midnight, while a 36-hour block is operated for the works related to the extension of platform nos 10 and 11 at CSMT to accommodate 24-coach trains.

At CSMT, 250 skilled and technically competent staff are working at CSMT station, as per the release.

The CR operated Panvel-CSMT trains till Wadala Road station, while trains on the Central Line were operated till Parel and Byculla stations.

Mumbai local train update: Trains cancelled

As per Central Railway, 930 suburban locals and 86 long-distance trains were cancelled during the 63-hour mega block. Of these, the highest 545 suburban services and more than 35 long-distance trains will remain cancelled on Saturday.

Besides the cancellation of local trains, many services were short-terminated and short-oriented on Saturday, officials added.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK