In a reply to an RTI activist, it has also been revealed that the BMC has allowed one of the contractors to push the deadline to May 2025
Mumbai Coastal Road
The BMC has already missed the deadline to open one arch bridge connecting the Coastal Road to Bandra Worli Sea Link by July end. In a reply to an RTI activist, it has also been revealed that the BMC has allowed one of the contractors to push the deadline to May 2025.
ADVERTISEMENT
The northbound and southbound roads of the Coastal Road from Nariman Point to Worli are already operational and work on the connectors have been delayed owing to the monsoon. Though the BMC assured that it would complete the entire road once it got a dry spell, the corporation also informed RTI activist, Anil Galgali, that it had extended the deadline for one of the contractors by 181 days and the new deadline would now be May 2025.
RTI activist Galgali had sought information from the BMC regarding the original date of completion of the Coastal Road Project and the current status.
BMC informed him that the original date of completion of work that was divided into four parts, was October 2022. This deadline has been extended thrice to May 2023, November 2023 and April 2024. Some of the work has been extended up to October 2024, too. Till date, 91 per cent of the work has been completed and the project work is in its final stage.
Bhushan Gagrani, municipal commissioner, told mid-day that an extension had been given to the work related to amenities such as parking zones, etc., and not to the actual pathways. The work of laying asphalt on the arch bridges will be completed soon once there was a dry spell and it would then be opened for commuters.