MMRCL to launch first phase of Metro-3 corridor in 2023

Updated on: 30 December,2022 09:34 PM IST  |  Mumbai
PTI |

In a release, the MMRCL said it received all eight coaches of the metro train, manufactured in the Alstom Plant in Sri City of Andhra Pradesh on Thursday, and these will undergo mandatory tests on a 5-km stretch between the ramp at Sariput Nagar and Sahar

MMRCL to launch first phase of Metro-3 corridor in 2023

Representational Pic. iStock

The Mumbai Metro Rail Corporation Limited (MMRCL) on Friday said it will roll out the first phase of Aarey-Bandra Kurla Complex (BKC) line of the Colaba-Bandra-SEEPZ Metro-3 corridor in 2023.


In a release, the MMRCL said it received all eight coaches of the metro train, manufactured in the Alstom Plant in Sri City of Andhra Pradesh on Thursday, and these will undergo mandatory tests on a 5-km stretch between the ramp at Sariput Nagar and Sahar.


We will roll the first phase of Metro Line-3 from Aarey to BKC, this 2023," MMRCL's managing director Ashwini Bhide said in the release.


It is significant to note that the first train has already undergone all dynamic and static tests through the trial runs of more than 1,500-kms successfully, she said.

As per the release, the MMRCL had completed tunnelling of the entire 54.5-km Up and Down line on November 30.

Also Read: Mumbai: First station erection work on metro line 4A has begun, says MMRDA

We required 17 tunnel boring machines (TBM) and 1,700 workmen to complete 100 per cent tunnelling for the 33.5-km long corridor," S K Gupta, director (projects) of MMRCL said.

A total of 2,86,000 cubic meters of concrete and 29,500 metric tonnes of steel was used for the huge task, and 50 per cent of the track laying work has been completed, the release said.

At least 105 escalators, 19 lifts, 10 platform screen doors and 12 passenger information display systems have been installed at various stations and the remaining work is in full swing, it stated.

This story has been sourced from a third party syndicated feed, agencies. Mid-day accepts no responsibility or liability for its dependability, trustworthiness, reliability and data of the text. Mid-day management/mid-day.com reserves the sole right to alter, delete or remove (without notice) the content in its absolute discretion for any reason whatsoever

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK