CR’s 5th and 6th line expansion stalled by land issues, bridge demolition delays

Updated on: 07 February,2025 10:30 AM IST  |  Mumbai
Rajendra B. Aklekar | rajendra.aklekar@mid-day.com

Among several hurdles is land acquisition between Kurla and CSMT; Dharavi bridge to be demolished only after Sion connector comes up.Six months after Sion bridge was shut in August, mid-day had highlighted how four trees and a toilet block were blocking the demolition of the structure. Railway authorities have written to the BMC

CR’s 5th and 6th line expansion stalled by land issues, bridge demolition delays

The Dharavi bridge, which will be replaced by a wider structure to accommodate the fifth and sixth lines. Pic/Ashish Raje

Listen to this article
CR’s 5th and 6th line expansion stalled by land issues, bridge demolition delays
x
00:00

The expansion of the fifth and sixth lines on Central Railway (CR), for which the Sion bridge is being demolished, is facing several hurdles, including the acquisition of about 14,626 sq m of land between Kurla and Chhatrapati Shivaji Maharaj Terminus (CSMT). After the Sion connector is reconstructed a few years from now, the Dharavi road overbridge will be razed, officials said. “The Dharavi bridge has been put on the demolition list to make way for a wider and bigger connector, but the work will only be undertaken after completion of the Sion bridge,” an official said.


Six months after Sion bridge was shut in August, mid-day had highlighted how four trees and a toilet block were blocking the demolition of the structure. Railway authorities have written to the Brihanmumbai Municipal Corporation (BMC), asking that hurdles to the demolition be removed speedily. The mail express line corridor comprising the fifth and sixth lines that start from Kalyan and end at Vidyavihar is being extended to Parel in phase one and all the way to CSMT in phase two.


Line expansion


This expansion will lead to the segregation of suburban and outstation trains all the way from Kalyan to CSMT. About 37 railway structures, signalling and electrical infringements are yet to be shifted on the alignment while 714 project-affected people reside on land that is yet to be acquired. The Mumbai Metropolitan Region Development Authority (MMRDA) is addressing their needs.

The harbour line platforms at Kurla will be shifted to an elevated level and the existing harbour line tracks will be converted into the fifth and sixth lines to maintain continuity. Mill land as well as the civic body and privately owned plots account for 14,626 sq m of land required to lay the new lines. While 5909.41 sq m of land belongs to the government, 8716.54 sq m is owned by private entities.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK