Home > Mumbai > Mumbai News > Article > Airoli Katai Naka Road work progressing rapidly MMRDA

Airoli-Katai Naka Road work progressing rapidly: MMRDA

Updated on: 11 March,2025 07:32 AM IST  |  Mumbai
Ranjeet Jadhav | ranjeet.jadhav@mid-day.com

3.43-km first phase comprising elevated road, twin tunnels likely to be ready by January 2026. Phase I of the project includes construction of a 3.43-km road connecting Thane-Belapur Road to NH-4. The elevated portion of the road, which has three lanes in either direction, is 0.935 km in length. Phase I also includes twin tunnels with four lanes

Airoli-Katai Naka Road work progressing rapidly: MMRDA

Sections of the 12.30-km Airoli-Katai Naka Road, which includes 1.68-km twin tunnels that run below Parsik hill. Pics/Sayyed Sameer Abedi

Listen to this article
Airoli-Katai Naka Road work progressing rapidly: MMRDA
x
00:00

Work on the Airoli-Katai Naka Road project—which will bring relief to motorists travelling from Airoli towards Kalyan, Dombivli, Ambernath and Badlapur—is progressing at a fast pace, according to officials.


Phase I of the project includes construction of a 3.43-km road connecting Thane-Belapur Road to NH-4. The elevated portion of the road, which has three lanes in either direction, is 0.935 km in length. Phase I also includes twin tunnels with four lanes in either direction measuring 1.68 km in length.


Sections of  the 12.30-km Airoli-Katai Naka Road, which includes 1.68-km twin tunnels that run below Parsik hill. Pics/Sayyed Sameer Abedi


A Mumbai Metropolitan Region Development Authority (MMRDA) official said, “The elevated section is complete while work on the tunnel portion is in progress. So far, 91.5 per cent of the tunnel work is finished.”

Phase II comprises a 2.57-km elevated link from Airoli bridge towards Thane-Belapur Road that has three lanes in either direction. According to the MMRDA, J Kumar Infraprojects Ltd is carrying out the work, 82 per cent of which has been completed.

Sections of  the 12.30-km Airoli-Katai Naka Road, which includes 1.68-km twin tunnels that run below Parsik hill. Pics/Sayyed Sameer Abedi

“Phases I and II are expected to be completed by January 2026 and September 2025, respectively,” the MMRDA official said.

The work on the 12.30-km Airoli-Katai Naka Road commenced in November 2017.

Once completed, the project, which comprises 1.69-km-long twin tube tunnels below Parsik hill, will help decongest traffic in Kalyan, Dombivli, Ambernath and Badlapur during morning peak hours.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK