A century later, Neral-Matheran railway line to be rebuilt

Updated on: 09 December,2021 10:22 AM IST  |  Mumbai
Rajendra B. Aklekar | rajendra.aklekar@mid-day.com

Existing line, which has been shut since 2019, is of a mix of old iron, steel and wooden sleepers which will now be upgraded with concrete sleepers

A century later, Neral-Matheran railway line to be rebuilt

Workers get concrete sleepers to lay on the track

Nearly three years after it was shut down, the Neral-Matheran line is set to chug again as the Matheran Light Railway is being rebuilt at a cost of Rs 5 crore, after over a century. The railways are using the template of track sleepers used in the Himalayan range of Kalka Shimla Railway for the project.


The two-feet narrow gauge line was built over a century ago in 1907 as a family enterprise of the Peerbhoys and is now in the UNESCO tentative list for Mountain Railways of India.



The railway line was built in 1907The railway line was built in 1907


The line had been running intermittently since the turn of the century. It was extensively damaged  in monsoon and has been shut since June 2019. However, a small stretch between Aman Lodge and Matheran was restored in December 2019.

“Yes. We are strengthening the line to the modern standards and for the first time re-laying the entire stretch with concrete sleepers,” said Central Railway Chief Public Relations Officer Shivaji Sutar.

The existing line is of a mix of old iron, steel and wooden sleepers which will now be upgraded with concrete sleepers. The sleepers are specially made at Khurda rail factory in Madhya Pradesh and are being transported to site.

“The line requires about 37,500 concrete sleepers of which around 2,500 have come so far and 35,000 are expected. In addition to sleepers, 800 metres of retaining wall, 1,300 m of gabion walls are being built and approaches are being strengthened,” he said, adding that the work is expected to complete in a year or so.

The line has also been nominated for the 2021 UNESCO-Greece Melina Mercouri International Prize. The award is given to outstanding examples of actions to safeguard and enhance the world’s cultural landscapes, a category of World Heritage.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK