Bad news Mumbai! The CST-Panvel fast corridor on CR faces hurdles

Updated on: 28 July,2016 05:38 PM IST  | 
PTI |

The Central Railway's much-awaited Chhatrapati Shivaji Terminus-Panvel fast corridor has hit a roadblock as the divisional administration has found few "hurdles" in implementing the project and has expressed its concerns to top officials

Bad news Mumbai! The CST-Panvel fast corridor on CR faces hurdles

The Central Railway's much-awaited Chhatrapati Shivaji Terminus-Panvel fast corridor has hit a roadblock as the divisional administration has found few "hurdles" in implementing the project and has expressed its concerns to top officials.


Vashi bridge
Vashi bridge


The Mumbai division of Central Railway, which would supervise the project, recently wrote a letter to the General Manager of the Central Railway (CR) saying that the project cannot be executed as it may cause frequent disruptions in suburban train operations. With this move, the plan to kickstart the ambitious project, worth over 14,000 crore, by the end of next month has hit a roadblock.


The 48.3 km long CST¿Panvel fast corridor was first proposed in the 2009-10 Railway Budget. It will be elevated for around 31 km of the route from south Mumbai to Vashi and for next 12.4 km, it will run parallel to the existing lines. The corridor will also require construction of a 4.3 km bridge over Thane creek.

A senior railway official said, "Yes, this is right that the Mumbai division of CR has apprised the General Manager of Central Railway about a few big impediments to execute the project."

"Out of the two major hurdles, the first is that during the execution of this infrastructural project, we would require unprecedented megablocks, that would throw suburban operations out of track. Also, it would be extremely difficult to construct the stations (on the fast corridor) over the (already existing) stations under strict caution," he said. He further refused to divulge details of the letter.

The Mumbai Railway Vikas Corporation (MRVC), a subsidiary of the Indian Railways, working with the state government which is responsible for improvement of infrastructure of Mumbai suburban railway system, had recently submitted the final plan for the corridor to the Railway Board following six years of deliberations.

When asked, a Central Railway spokesperson said, "We are trying to iron out all the issues, because it's a major infrastructural project that would give a big boost to our transportation system in the corridor."

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!


Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK