23 April,2023 07:10 AM IST | Mumbai | A Correspondent
Repair work being undertaken inside a tunnel
After a month-and-a-half-long wait, the city's water supply is going to be restored from today, BMC said. The city gets water from two major lines - a 2.5-metre diameter line from Tansa and 5.5-metre diameter tunnel from Bhatsa.
The first damage occurred on March 3 at Kopri in Thane when a 2.5-metre line leaked during the construction of a bridge. On March 27, the water main line near Mulund octroi naka was damaged during MSRDC's construction work of a box culvert. Major disruption occurred when the 5.5-metre diameter tunnel was punctured at Wagle Estate, during illegal digging for a bore well on March 28.
Also read: Mumbai: Water supply to be back to 100 per cent from April 23
ALSO READ
Mumbai rains: Train services and University exams cancelled
NDRF teams deployed in Mumbai to prevent flooding amid heavy rains
Heavy rains lash Mumbai, several areas inundated; trains disrupted
EXCLUSIVE: More trouble for officer accused in Ghatkopar hoarding collapse case
Mumbai: Merchant kidnapped, rescued by cops in 2 hrs
Soon after, the BMC announced a month-long 15 per cent water cut to undertake repair work. As the BMC was preparing for repair, the 2.5-metre line was damaged for the second time in Kopri. "With all the leakages fixed, the water supply has been restored and the city will get water like usual," said Purushottam Malawade, chief of the Hydraulic Engineering Department.