22 July,2021 09:23 AM IST | Mumbai | IANS
Mumbai metro train. Pic/AFP
Spelling cheers for Mumbaikars, almost 97 per cent tunnelling work on the longest and fully-underground Colaba-Bandra-SEEPZ Mumbai Metro 3 corridor has been completed with the 39th breakthrough achieved at Mahalaxmi, officials said on Wednesday. Till date, the Mumbai Metro Rail Corporation (MMRC) Ltd, which is executing the project, has tunnelled 52.60 km of the 54.50 km double line (up/down), marking nearly 97 percent of the total tunnelling work required, company's Managing Director Ranjit Singh Deol said.
The city's first fully subterranean 33.50-kms long Colaba-Bandra-SEEPZ Metro-3 line, which passes below sections off the Mithi River and Mahim Creek, will have 27 stations, including 26 underground, with at least 6 inter-changes at strategic points on the route. Estimated to cost around Rs 23,136 crore, the entire project is expected to be operational by mid-2022, and transport around 1.60 million commuters daily in full comfort.
In the ongoing work, the latest achievement was the breakthrough at Mahalaxmi Metro Station by the tunnel boring machine Tansa-2, completed in 257 days, using 745 concrete rings, Deol said. "This was a challenging task as this stretch from the Science Museum Metro Station to Mahalaxmi Metro Station encompasses tunnelling below the buildings which are more than 80 years old and live Western Railway tracks between Mahalaxmi-Lower Parel railway stations," he said.
This work was part of the longest - Package-3 in the total project - which includes Mumbai Central, Mahalaxmi, Science Museum, Acharya Atre Chowk, and Worli metro stations, and has witnessed three major breakthroughs so far. Officials say that by 2022-end, Mumbai would get at least 3 new Metro lines which will make commuting much easier besides reducing the load on the city roads and the two highways. Simultaneously, the work on other Metro routes by the Mumbai Metropolitan Region Development Authority is proceeding at full swing in different parts of the city and surroundings.
ALSO READ
Male, female vote share increase similar across state
Maharashtra Assembly Elections 2024: Bhandup registers highest voter turnout
Maharashtra polling percentage: Mumbai, including laggard Colaba, does better; slight dip in suburbs
Colaba records low voter turnout yet again despite robust awareness initiatives
Colaba's poor run continues; records 41.64 per cent voter turnout in polls
This story has been sourced from a third party syndicated feed, agencies. Mid-day accepts no responsibility or liability for its dependability, trustworthiness, reliability and data of the text. Mid-day management/mid-day.com reserves the sole right to alter, delete or remove (without notice) the content in its absolute discretion for any reason whatsoever