01 March,2021 07:03 AM IST | Mumbai | Rajendra B. Aklekar
Work on Delisle Road bridge near Lower Parel station is going on in full swing. Pic/Ashish Raje
AMID the subdued pace of Mumbai due to the COVID-19 pandemic, the key Delisle Road bridge is quietly rising near one corner of the Lower Parel station. The work above the rail tracks is expected to be complete in two months.
The deep foundations of the bridge were laid on the either side of the tracks in January and the web girder that is being assembled is now expected to get ready in April. An engineer said the girder has been designed keeping in mind that the bridge needs to be placed at an angle of 65 degrees, matching with the alignment of its earlier avatar. The bridge has come up on a skeleton of 360 metric tonnes of stainless steel covered by 3,700 cubic metres of robust M-40 concrete.
The dismantling work of the spans over railway tracks was completed in February 2019, in a record five months. This was followed by removal of abutments in June 2019 after the civic body cleared encroachments. The Western Railway then awarded the contract for rebuilding the railway portion for R87 crore and work started in November that year. The foundation on the east side was completed in May 2020 and completion of the raft foundation on the west side was in June 2020 and east side by January 2021.
Once WR's work is done, the BMC will build three approaches - two on the west for dismantling and rebuilding and one on the east for assembly and placing the girders that cannot be lifted and launched without being pushed. The dismantling and rebuilding of the approaches is expected to be complete by March 2022.
ALSO READ
Bengaluru: Case registered in connection with COVID-19 mismanagement
Biden commutes roughly 1,500 sentences, pardons 39
Morocco produces Africa’s first test kits to fight Mpox
Covid virus lurks in skull and brain meninges for years after infection: Study
‘Misguided, forced to take Covid vaccines’
360
Quantity in tonnes of steel used to build the girder