21 June,2022 07:47 AM IST | Mumbai | Rajendra B. Aklekar
The work is on at Vikhroli station and is likely to be complete in the next 2 days
A promise made is a promise kept. As Central Railway General Manager Anil Kumar Lahoti had assured mid-day 10 days ago, the work on installing roofs at stations has begun at a rapid pace and the work has even been completed at a few stations. Kurla station got its roof within eight days while the work for Vikhroli station, where the roof was removed for a new foot overbridge, is on and set to be complete in two days.
The work at Bhandup station is complete on platforms 2 and 3 and work on placing the roof at the base of the new two-way escalator on platform 1 is in its last stages. "A comprehensive review of all such pending works has been done and all the missing elements at all stations are being fixed on a priority basis," a CR spokesperson said. mid-day has been following up the issue of leaking and missing platform roofs at railway stations before the monsoon sets in. While divisional officials had assured action, there were no immediate results seen on the ground.
The work on placing the roof of the new two-way escalator on platform no. 1 at Bhandup station is in its last stages
Lahoti in an interview to mid-day on June 10 had promised a complete review of the works and said that the problem would be addressed at a priority level. Complaints have also been received about the missing roof of extended platforms at Masjid Bunder station, but due to the narrow tapering platform and lack of dimensions for a traditional roof, it may hamper safe movement of trains with a smaller roof having stability issues. With works on new bridges, escalators and elevators at several stations, there remains a gap even after completion of the bridge. Commuters had suggested that if work is not complete, at least temporary roofing should be erected at stations for the monsoon period to do away with inconvenience.
ALSO READ
Mumbai: Unknown metal object hits train commuters near Bhandup, GRP probes
Mumbai local train updates: Commuters stranded as AC train doors fail to open
Railways plan two new bridges at Prabhadevi station, one will connect Parel
CR to operate mega block on Sunday, check details
CR to run 10 special train trips between Mumbai, Nagpur for RRB exam candidate
8
No. of days within which the roof at Kurla station was installed
2
Days required to complete the work at Vikhroli station