08 August,2020 07:30 AM IST | Mumbai | Rajendra B Aklekar
Tunnelling works at Pernem was completed around January 10, 1998
A wall collapse inside the Pernem tunnel on Thursday morning has paralysed the services on Konkan Railway (KR) and the trains are now being diverted via Miraj-Pune route. A KR note said eight trains will be diverted till August 20.
Old-timers and KR records recall how Pernem tunnel has always been a problem, which alone had delayed the entire KR project for five months. KR has 91 tunnels, adding up to 84 km in length. However, tunnels totalling 3,500 metres in length on weak soil, mainly in Goa and Karnataka, posed the most problems during construction. Recalling the construction days, former managing director Dr E Sreedharan said, "The soil in the tunnels became like toothpaste. The unexpected geology and soft soil in Pernem and Old Goa tunnels were leading to accidents and collapses."
"Pernem is a 1,560-metre-long tunnel. Work on this had started in January 1992, first on the north-face and later on the south-face. The excavation was difficult as the soil was mixed with both hard and soft rocks and then soil. In the monsoon of 1992, both the north and south end collapsed, taking three months for rectification. Again in 1993 monsoon, more collapses occurred. Such collapses continued till 1997 and strategy had to be altered every time. This tunnel took the longest time to complete," explains former engineer and advisor SV Salelkar in his book 'A treatise on Konkan Railway.' In the Pernem tunnel, eight fatalities have occurred at different times after rocks caved in during excavation.
Tunnelling works at Pernem, which cost R6.49 crore was completed around January 10, 1998. Only after this, the last section on the KR between Sawantwadi and Pernem (22 km) was opened for traffic on January 26, 1998 - states another book Konkan Railway, 'A Dream Come True.'
ALSO READ
Shiv Sena big in Konkan, Ajit Pawar wrests West, BJP Shines all over
Uddhav Thackeray to start campaign on Nov 5 from Konkan and Vidarbha
Konkan's political shift: From Congress stronghold to rival Sena battleground
Video of Ratnagiri stn's flapping roof sheet rouses questions on quality of work
A Goan fiesta in Mumbai
Another engineer SS Bhatnagar recalled how while work on the tunnel was underway, Dr Sreedharan had to procure a specially identified hi-tech machine from Germany and get it air-freighted to India.
Narendra Singh Tomar and Railway Minister Piyush Goyal on Friday flagged off a train for farmers called âKisan Rail' to provide a seamless supply chain of agricultural and perishable produce between Devlali in Nashik to Danapur. Officials said given the high production of onions near Nashik, the train will be beneficial for farmers to transport their produce. This train will have 10 parcel vans and one luggage cum brake van and will cover a distance of 1,519 km in 31.45 hrs on one trip.
Catch up on all the latest Mumbai news, crime news, current affairs, and a complete guide from food to things to do and events across Mumbai. Also download the new mid-day Android and iOS apps to get latest updates.
Mid-Day is now on Telegram. Click here to join our channel (@middayinfomedialtd) and stay updated with the latest news