03 September,2018 02:08 PM IST | Mumbai | Rajendra B Aklekar
Achal Khare, MD, NHSRCL
The Managing Director of National High Speed Rail Corporation Limited (NHSRCL) Achal Khare spoke with mid-day.
What is the status of land acquisition and surveys in Palghar?
Of the total 508 km, about 110 km passes through Palghar district, affecting 74 villages. Of these, we have completed survey in about 28 villages; in the rest it's under process.
Villagers seem to be opposing it. How much land will be affected?
Please understand that we do not require much land as the railway line is 15-metre high on a viaduct. Only 17.5 metres, or 60 feet, is required to put in pillars. This stretch will have a service road, below the viaduct stretch, for maintenance of trains. The service road will become a public road, and villagers can use it.
There is too much confusion among villagers. When will there be more clarity?
It is important to note that most of the landowners who are affected are talking to us directly and do not seem to have a problem. It is the other villagers, ones not connected with the land, who are floating stories and creating confusion. Much of the protest and opposition has political flavour, which I don't want to get. There will be more clarity as days pass. We intend to complete land acquisition by December.
ALSO READ
Mumbai airport hosts vibrant celebrations with Ganpati Palkhi Parade
24,000 cops to man streets as Mumbai gears up for Anant Chaturdashi on Sept 17
Aaditya Thackeray visits Pune's Shrimant Bhausaheb Rangari Ganpati Mandal
BMC union demands early declaration of Diwali bonus ahead of polls
Police conducts route march ahead of Ganesh Visarjan and Eid-e-Milad
Catch up on all the latest Mumbai news, crime news, current affairs, and also a complete guide on Mumbai from food to things to do and events across the city here. Also download the new mid-day Android and iOS apps to get latest updates