22 December,2019 07:00 AM IST | Mumbai | Rajendra B Aklekar
The bridge has been shut since July 24, 2018. Pic/Ashish Raje
Work on the city's most-awaited road bridge at Lower Parel is finally underway, with piling work for foundations in place. The project is expected to be complete by mid-2021.
The Delisle Road Over Bridge at Lower Parel station has been closed for traffic since July 24, 2018, as it was declared unsafe and later dismantled.
A Western Railway spokesperson said micropiling work is being conducted at night so that the locals are not disturbed. Sources said this basically means that the rail track will remain stabilised once digging for foundations and other processes begin.
ALSO READ
WR announces major block at Lower Parel during night of December 27-28
KOKO to host a bar takeover by one of Asia's best, Sago House today
Fire breaks out at railway shunting coach of train in Lower Parel
Mahaparinirvan Diwas 2024: Mumbai Police announces traffic advisory
Experience the culinary flavours of Kerala at this resto-bar in Lower Parel
"The micropiling work began a month ago on November 14 and is already half complete. Once this is done, a period of 40 days has been earmarked for this, the digging and setting of foundations shall begin on either side of the rail lines. The project is being done in co-ordination with the BMC," an official added.
This has been a difficult bridge to demolish, and reconstruct as it was skewed in design, standing at 64 degrees to the rail tracks. When mid-day visited the bridge last week, work was on near the slow line and land for the foundation had been cleared on the east side too.