07 June,2014 03:03 PM IST | | Ranjeet Jadhav
Mumbaikars have ample reason to celebrate as they will be able to travel in air-conditioned comfort in the 11.04 km Versova Andheri Ghatkopar metro rail corridor from Sunday morning
Mumbaikars will be able to travel in the 11.04 km Versova Andheri Ghatkopar metro rail corridor from Sunday morning.
Also read: Mumbai Metro likely to start in a week's time
Speaking to MiD DAY Mumbai Metro One Private Limited (MMOPL) CEO Abhay Mishra said," VAG Metro line will be operational for public from Sunday morning. "
If the sources are to believed then the issue of what will be the metro fares has also been sorted out between MMOPL and MMRDA and the fares are expected to be minimum of Rs 10 and Maximum of Rs 40.
Total length: 11.04 km
Total stations: 11
Actual project cost when the contract was awarded: Rs 2356 crore
Present project cost- over: Rs 4200 crore
Train timings: Metro will from 5.00 am till midnight.