17 December,2020 10:48 AM IST | Mumbai | IANS
Work midway at underground Metro Railway | File pic
The Mumbai Metro Rail Corporation Ltd on Wednesday announced that nearly 90 per cent of the tunnelling work on the 33.5 km long fully underground Colaba-SEEPZ Mumbai Metro Line 3 has been completed.
Of the 54.50 km dual tunnel for up and down lines, the MMRCL has till date completed 49.50 km tunnelling, for the city's first fully underground Metro Line 3, a portion of which will go underneath the Mithi River.
The latest breakthrough was achieved at Dadar Metro Station with the completion of the 1.12 km long tunnel from the Siddhivinayak Temple to Dadar, marking the completion of the 10.96 km tunnel under the Package 4.
"The tunnelling work, using 3 Tunnel Boring Machines, in 4 out of the total 7 packages is now 100 per cent complete. The tunnelling in Package 4 was particularly challenging as all stations are located in close proximity to developments, active road traffic and important religious sites," said MMRCL Managing Director Ranjit Singh Deol.
ALSO READ
Maharashtra elections 2024: What does Mumbai’s GenZ want from political leaders?
More trains, Metro services but less buses on election day
Maharashtra polls: MMRC extends service hours for election day
Forest department launches probe into mysterious jackal deaths
BKC traffic tangle: Experts call for a total reset
He said that Dadar, considered the heart of the city, will provide connectivity that will ease commuting woes of the Mumbaikars, on the Line 3.
MMRCL's Director (Projects), S.K. Gupta said that the Herrenknecht-made TBMs, equipped with earth pressure balance technology, started its main tunnelling drive on July 7 and completed the stretch using 805 rings, and now the overall progress of Dadar Metro Station is around 42 per cent.
The Package 4 included Siddhivinayak Temple, Dadar, and Shitladevi stations with 8 important breakthroughs at various locations on the Colaba-SEEPZ alignment, which will cater to some of the most important business and residential locations including the Mumbai International Airport.
It also includes a 170-metre long dual-tunnel passing under the Mithi River on the Dharavi-Bandra Kurla Complex sector, making it India's second under-river tunnel after the one underneath Hooghly River in the Kolkata Metro.
Catch up on all the latest Crime, National, International and Hatke news here. Also download the new mid-day Android and iOS apps to get latest updates.
Mid-Day is now on Telegram. Click here to join our channel (@middayinfomedialtd) and stay updated with the latest news
This story has been sourced from a third party syndicated feed, agencies. Mid-day accepts no responsibility or liability for its dependability, trustworthiness, reliability and data of the text. Mid-day management/mid-day.com reserves the sole right to alter, delete or remove (without notice) the content in its absolute discretion for any reason whatsoever