10 August,2019 10:36 AM IST | Mumbai | Ranjeet Jadhav
Pic/Ranjeet Jadhav
The Mumbai Metropolitan Region Development Authority (MMRDA) on Friday announced that the segment casting for Bridge Deck construction of the Mumbai Trans Harbour Link project connecting Sewri with Nhava Sheva has been completed.
In a press release, the authority has stated that the pre-cast segment casting, which is a pre-cursor to the superstructure of Bridge Deck Construction, has been completed and it was done in the presence of MMRDA Additional Metropolitan Commissioner, Sanjay Khandare.
"The completed 75-tonne segment, with a dimension of 14.8m length x 3.32m width x 3.85m height, will be erected in the marine section at a distance of 6-km inside the sea. This is India's longest water bridge", informed Khandare.
Also Read: MMRDA's 20-year MTHL dream to be reality soon
ALSO READ
Mumbai Metro launches WhatsApp ticketing service for Lines-2A and 7
Mumbai: Service roads revamp part of big plan to concrete entire WEH, EEH
Mumbai Metro Line 3: No relief for university folk
Mumbai: 50 recycled plastic benches installed at key locations in BKC
Mumbai Metro Line 3: Don’t set off to airport yet
The progress on the project is said to be noteworthy, with MMRDA completing 270 permanent piles, of which 177 have been completed in the sea. The project has also completed 2-km of Temporary Access Bridge - which includes both sides - 16 pile caps and 10 piers.
Moreover, the work of very first 8-meter tall pier of the crucial Mumbai Trans Harbour Link Project is already completed at Sewri. As of now, in all, 114 piles have been completed along with 3 pile caps. The 22-km long MTHL will help people reach island city faster, saving travel time and fuel.
Catch up on all the latest Mumbai news, crime news, current affairs, and also a complete guide on Mumbai from food to things to do and events across the city here. Also download the new mid-day Android and iOS apps to get latest updates