06 August,2018 10:54 PM IST | Mumbai | PTI
Bombay High Court
The Bombay High Court has sought to know from the city's civic body about the progress on the setting up of stormwater pumping stations at three suburban locations.
Under the Brihanmumbai Storm Water Drain (Brimstowad) project launched by the BMC after the July 26, 2005 deluge in Mumbai, eight stormwater pumping stations were to be built across the city of the eight, five pumping stations are already functional.
A division bench of justices Ranjit More and Anuja Prabhudessai was hearing a public interest litigation (PIL) petition filed by advocate Atal Bihari Dubey, seeking for a second doppler radar system for Mumbai and other measures to be taken to ensure that people do not suffer due to floods during monsoons.
Last week, the petitioner's counsel, S C Naidu, told the court that the civic body had, till date, not made the storm water pumping stations at Gazder Bund in Santacruz, Mogra in Andheri and another in Mahul functional.
ALSO READ
Advocate pursuing MPhil alleges MU's law dept tampered with his answer sheets
Bomaby HC upholds tender awarded to Adani Group for Dharavi slum project
Bombay HC dismisses plea against Sena leader Ravindra Waikar's win in LS polls
Mumbai: Hawkers ply wares right next to BMC van
Badlapur sexual assault case probe complete; cop suspended: SIT to HC
"The BMC is directed to file affidavit on August 23, placing on record the progress regarding stormwater pumping stations at these three locations," the court said.
Catch up on all the latest Crime, National, International and Hatke news here. Also, download the new mid-day Android and iOS apps to get latest updates