50 per cent work on second tunnel of Mumbai Coastal Road completed, says BMC

30 July,2022 01:43 PM IST |  Mumbai  |  PTI

In a release issued on Friday, the civic body said work on the 1,000 metre stretch of the second tunnel of the Coastal Road has been completed

Representational image


The Brihanmumbai Municipal Corporation (BMC) has completed 50 per cent work on the second tunnel of the Coastal Road project between Girgaum Chowpatty and Priyadarshini Park, an official said on Saturday.

In a release issued on Friday, the civic body said work on the 1,000 metre stretch of the second tunnel of the Coastal Road has been completed.

The excavation work for the 2 km-long second tunnel with a diameter of 12.49 metre began on January 11 this year.

Also read: Mumbai: Worli fisherfolk threaten to stop Coastal Road work

The work for the Coastal Road project, which is estimated to cost Rs 12,721 core, is expected to be completed in December 2023.

The Coastal Road project will comprise twin tunnels dug 10 to 70 metres below the surface between Girgaum Chowpatty and Priyadarshini Park using India's largest TBM (tunnel boring machine) ‘Mawla'.

The tunnels will be interconnected with seven locations, of which four will be used for vehicles. The tunnels will have emergency control rooms with automated systems.

This story has been sourced from a third party syndicated feed, agencies. Mid-day accepts no responsibility or liability for its dependability, trustworthiness, reliability and data of the text. Mid-day management/mid-day.com reserves the sole right to alter, delete or remove (without notice) the content in its absolute discretion for any reason whatsoever.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!
brihanmumbai municipal corporation mumbai news
Related Stories